Mother Teresa Catholic College – Baldivis

TES worked closely with our client to ensure that all of our works remained segregated from the operational school and to ensure that all risks were minimized to have no impact on the College’s operations.

Find Out More

Mother Teresa Catholic College – Baldivis

TES worked closely with our client to ensure that all of our works remained segregated from the operational school and to ensure that all risks were minimized to have no impact on the College’s operations.

Mother Teresa Catholic College – Baldivis

The Project

Following the successful completion of Stage 3, TES was awarded the Stage 3A contract to provide the extended Learning Block part 2, Resource Centre/Science Block and Administration block.

General learning areas, science and administration buildings comprise of double-storey rammed earth walls, pushing the use of the material beyond just aesthetic but also structural, unique in its design as there are no additional structural steel columns contained within.

All learning areas within the design were orientated to optimize passive solar effects and capture breezes for natural ventilation, which coupled with the thermal mass of the rammed earth walls will minimize overall energy usage of the building. This is also all automated on a fully integrated BMS system.

TES worked closely with our client to ensure that all of our works remained segregated from the operational school and to ensure that all risks were minimized to have no impact on the College’s operations.

Overview

TES Electrical were contracted to carry out the following works, including supply, installation and commissioning of the systems:

  • Connection to the existing generator, automatic transfer, and essential distribution installation.
  • Building Main Switchboard and Sub Distribution Boards, inc. kWh metering and surge protection.
  • Earthing Systems.
  • Building Lightning Protection System.
  • Mains & sub-mains cabling.
  • Provision of general and specialized lighting throughout the complex including luminaires and specialist controls.
  • General power installation throughout.
  • Communication and Structured cabling installation.
  • Fire Detection, Emergency Warning & Intercommunications Systems (EWIS).
  • MATV System.
  • Security, Access Control & CCTV System.
  • Uninterruptable power supply (UPS).
  • Power Factor Correction Unit.
  • Fire Sealing of Penetrations.
  • Testing and Commissioning.

Timeline

The project commenced in November 2017 and was completed in March 2019. Works were completed on time and project was met to client’s satisfaction.

Return to projects